Building of a production hall Zell a. H.

Gissler is a metal-working company for steel machining. The main machining processes are sawing, milling, turning and grinding.

In order to expand the poduction capacity, a new production hall with a ground-plan area of almost 1,100 m² was built in 2011. It was erected as a saddle roof hall with an eaves height of about 6 m and a ridge height of about 7.70 m.

The roofing and the panelling were effected with foam-filled steel sandwich panels. A ridge roof light ribbon provides for sufficient daylight in the hall. Horizontal aluminium ribbon windows with built-in ventilation flaps replenish the daylight yield and provide for light at the workplaces.
Müller Offenburg delivered the complete building shell.